Nine projects. Including the numbers that went the wrong way.

We publish contract values, durations, peak workforce and safety results because a portfolio where every project finished early and under budget is not a portfolio, it is a brochure. Two of the nine below were difficult. One is described in full, including what it cost us.

$1,402M Combined contract value

Across the nine projects on this page, 2019–2026.

9 Markets and delivery methods

Design-build, CMAR, design-bid-build and contract mining.

11.4M Hours worked

With one lost-time incident and four recordable injuries in total.

7 Delivered early

Seven of nine reached substantial completion at or ahead of contract date.

Filter the portfolio

Find work like yours.

Filter by market or delivery method. Each record below is a real contract of ours; details on any of them, references, final cost, lessons learned, are available to owners who ask.

Showing 9 of 9 projects

Heavy Civil · Design-Build

I-70 Floyd Hill Reconstruction, Segment 3

Clear Creek County, Colorado

Widening and realignment of 3.4 miles of interstate through a geologically active mountain corridor, including two new structures over Clear Creek and a full interchange replacement.

  • ClientColorado Department of Transportation
  • Value$214M
  • Period2022 – 2026

Energy · Design-Bid-Build

Cascade Ridge Pumped Storage, Balance of Plant

Chelan County, Washington

Civil, hydraulic and electrical balance-of-plant for a 380 MW pumped storage facility, delivered inside a 42-month energisation window.

  • ClientCascade Power Authority
  • Value$388M
  • Period2021 – 2025

Mining · Contract Mining

Bighorn Basin Pre-Strip & Contract Mining

Campbell County, Wyoming

Ongoing overburden removal and coal delivery under a five-year term contract, moving approximately 46 million bank cubic yards per year.

  • ClientThunder Basin Resources LLC
  • Value$172M
  • Period2019 – present

Government · CMAR

Red Mesa Water Reclamation Facility

Maricopa County, Arizona

A 24 million gallon per day advanced water reclamation facility providing recharge supply and drought resilience for a 520,000-person service area.

  • ClientCity of Mesa & U.S. Bureau of Reclamation
  • Value$94M
  • Period2023 – 2026

Government · Design-Build

Tinker AFB Hangar 3003 Modernization

Oklahoma City, Oklahoma

Full modernization of a 1960s-era maintenance hangar into a high-bay aircraft sustainment facility, executed adjacent to active flight-line operations.

  • ClientU.S. Army Corps of Engineers, Tulsa District
  • Value$67M
  • Period2022 – 2024

Mining · Design-Build

Antofagasta Copper Concentrator Expansion

Antofagasta Region, Chile

Concentrator throughput expansion from 78,000 to 120,000 tonnes per day, including new grinding circuit and flotation bank, at 3,100 metres elevation.

  • ClientAndean Copper Joint Venture
  • Value$245M
  • Period2020 – 2024

Energy · Design-Bid-Build

Denali 230 kV Transmission Rebuild

Lewis County, Washington

Rebuild of 41 route miles of ageing 230 kV wood-pole line to steel monopole construction, delivered entirely under planned outage windows.

  • ClientCascade Power Authority
  • Value$58M
  • Period2023 – 2025

Industrial · Design-Build

Bluegrass Rail & Bulk Terminal

Louisville, Kentucky

Greenfield 42-acre multimodal bulk terminal with barge unloading, rail loop and 180,000 tonnes of covered storage.

  • ClientOhio River Terminals Group
  • Value$121M
  • Period2021 – 2024

Government · Design-Bid-Build

Rio Grande Levee Restoration, Reach 4

Doña Ana County, New Mexico

Rehabilitation of 14.2 miles of levee to FEMA and USACE 100-year flood protection standards, including slurry cutoff wall and habitat restoration.

  • ClientU.S. Army Corps of Engineers, Albuquerque District
  • Value$43M
  • Period2023 – 2025

Case studies

What the work actually involved.

Scope, delivery approach and outcome for each project. Where a project ran into trouble, that is in here too.

Heavy Civil · Design-Build · 2022 – 2026

I-70 Floyd Hill Reconstruction, Segment 3

Widening and realignment of 3.4 miles of interstate through a geologically active mountain corridor, including two new structures over Clear Creek and a full interchange replacement.

Owner: Colorado Department of Transportation
Location: Clear Creek County, Colorado
Contract value: $214M

Back to portfolio →

Illustration of a concrete arch bridge with pier columns at dusk

Scope delivered

  • 1.1 million cubic yards of rock excavation, restricted blasting within 180 feet of an active travel corridor
  • Two cast-in-place segmental structures, 1,140 feet total length
  • Full diamond interchange replacement under staged traffic
  • Permanent ground anchorage and rockfall mitigation
  • Intelligent transportation system and fibre backbone
  • Contract typeProgressive design-build
  • Self-perform78%
  • Peak workforce412
  • Recordable incidents0

Energy · Design-Bid-Build · 2021 – 2025

Cascade Ridge Pumped Storage, Balance of Plant

Civil, hydraulic and electrical balance-of-plant for a 380 MW pumped storage facility, delivered inside a 42-month energisation window.

Owner: Cascade Power Authority
Location: Chelan County, Washington
Contract value: $388M

Back to portfolio →

Illustration of a dam, spillway and gate structures

Scope delivered

  • Intake and outlet structures, 1,900 feet of 22-foot diameter penstock
  • Powerhouse cavern excavation and concrete lining
  • 230 kV switchyard and generator step-up transformer installation
  • Tailrace and upstream cofferdam construction
  • Fish passage and aquatic habitat mitigation
  • Capacity380 MW
  • EnergisedOn schedule
  • Concrete placed184,000 CY
  • EMR on site0.48

Mining · Contract Mining · 2019 – present

Bighorn Basin Pre-Strip & Contract Mining

Ongoing overburden removal and coal delivery under a five-year term contract, moving approximately 46 million bank cubic yards per year.

Owner: Thunder Basin Resources LLC
Location: Campbell County, Wyoming
Contract value: $172M

Back to portfolio →

Illustration of terraced open-pit mine benches with haul equipment

Scope delivered

  • Drill, blast and overburden removal, 46M BCY annually
  • Coal haulage and blending to plant feed specification
  • Haul road construction and continuous maintenance
  • Surface water management and sediment control
  • Progressive reclamation and bond release documentation
  • Term5 years, extended
  • Fleet34 owned prime movers
  • Availability93.1% three-year avg.
  • MSHAZero 104(d) citations

Government · CMAR · 2023 – 2026

Red Mesa Water Reclamation Facility

A 24 million gallon per day advanced water reclamation facility providing recharge supply and drought resilience for a 520,000-person service area.

Owner: City of Mesa & U.S. Bureau of Reclamation
Location: Maricopa County, Arizona
Contract value: $94M

Back to portfolio →

Illustration of a water reclamation facility with gate structures

Scope delivered

  • Membrane bioreactor and reverse osmosis process trains
  • 24 MGD average, 36 MGD peak hydraulic capacity
  • Recharge basins and 11 miles of transmission main
  • Solar-ready electrical backbone and standby generation
  • SCADA integration with existing city operations centre
  • Capacity24 MGD average
  • DeliveryCMAR, GMP
  • Buy AmericaCompliant
  • Recycled content31% of structural steel

Government · Design-Build · 2022 – 2024

Tinker AFB Hangar 3003 Modernization

Full modernization of a 1960s-era maintenance hangar into a high-bay aircraft sustainment facility, executed adjacent to active flight-line operations.

Owner: U.S. Army Corps of Engineers, Tulsa District
Location: Oklahoma City, Oklahoma
Contract value: $67M

Back to portfolio →

Illustration of an industrial aircraft hangar structure

Scope delivered

  • Structural strengthening and 42-foot high-bay door replacement
  • Anti-fatigue flooring and fall-protection systems
  • Compressed air, exhaust extraction and fuel systems
  • Hazardous materials abatement under phased occupancy
  • LEED Silver certification and commissioning
  • ContractFirm-fixed-price
  • OccupancyMaintained throughout
  • ScheduleDelivered 6 weeks early
  • Deficiency noticesZero

Mining · Design-Build · 2020 – 2024

Antofagasta Copper Concentrator Expansion

Concentrator throughput expansion from 78,000 to 120,000 tonnes per day, including new grinding circuit and flotation bank, at 3,100 metres elevation.

Owner: Andean Copper Joint Venture
Location: Antofagasta Region, Chile
Contract value: $245M

Back to portfolio →

Illustration of an open-pit copper mine with terraced benches

Scope delivered

  • SAG mill and ball mill foundations, 4,100 cubic metres each
  • Structural steel erection, 9,800 tonnes
  • Flotation circuit, thickeners and tailings pumping
  • High-altitude concrete practice and cold-weather enclosure
  • Bilingual workforce of 1,340 at peak
  • Elevation3,100 m
  • Throughput120,000 tpd
  • Local content62% Chilean suppliers
  • Safety4.1M hours, zero LTI

Energy · Design-Bid-Build · 2023 – 2025

Denali 230 kV Transmission Rebuild

Rebuild of 41 route miles of ageing 230 kV wood-pole line to steel monopole construction, delivered entirely under planned outage windows.

Owner: Cascade Power Authority
Location: Lewis County, Washington
Contract value: $58M

Back to portfolio →

Illustration of lattice transmission towers carrying high-voltage conductors

Scope delivered

  • 41 route miles of steel monopole construction
  • Helicopter-set structures in environmentally sensitive terrain
  • Two new 230 kV switching stations
  • Reconductor with composite core conductor
  • Wildfire risk reduction and vegetation management
  • Route miles41
  • Outages11 planned windows
  • ReliabilityZero unplanned
  • WildfireRisk class reduced 2 tiers

Industrial · Design-Build · 2021 – 2024

Bluegrass Rail & Bulk Terminal

Greenfield 42-acre multimodal bulk terminal with barge unloading, rail loop and 180,000 tonnes of covered storage.

Owner: Ohio River Terminals Group
Location: Louisville, Kentucky
Contract value: $121M

Back to portfolio →

Illustration of a bulk terminal with storage silos and pipe rack

Scope delivered

  • Barge unloader and 6,400 feet of marine works
  • 18,000-foot rail loop and two ladder tracks
  • 180,000 tonnes covered storage and reclaim tunnels
  • Dust suppression, water treatment and stormwater systems
  • Truck scale, gate automation and terminal management system
  • Site area42 acres
  • Marine works6,400 linear feet
  • Rail18,000-foot loop
  • Throughput4.2M tonnes/year

Government · Design-Bid-Build · 2023 – 2025

Rio Grande Levee Restoration, Reach 4

Rehabilitation of 14.2 miles of levee to FEMA and USACE 100-year flood protection standards, including slurry cutoff wall and habitat restoration.

Owner: U.S. Army Corps of Engineers, Albuquerque District
Location: Doña Ana County, New Mexico
Contract value: $43M

Back to portfolio →

Illustration of construction crews working along a flood control embankment

Scope delivered

  • 14.2 miles of levee reconstruction and raising
  • Soil-bentonite slurry cutoff wall, 62,000 square feet
  • Six drainage structures with flap gates
  • Riprap and vegetated bank stabilisation
  • Native riparian revegetation, 38 acres
  • Length14.2 miles
  • Protected asset value$1.8B
  • CulturalTribal monitor on site
  • AccreditationFEMA 100-year standard

Difficult projects

What happens when it goes wrong.

Two projects in the portfolio above did not go to plan. One is the 2017 water reclamation package we have already discussed elsewhere on this site. The other is below, a project where the ground was not what the geotechnical report said it was, and where the schedule consequence landed on us.

Rio Grande Levee Restoration, Reach 4, $43M

What happened. The contract documents indicated continuous lean clay over the full 14.2-mile reach. At mile 6.4 we encountered a 900-foot lens of loose saturated sand underlying the levee prism. The specified method, excavate and recompact in place, could not produce a stable embankment, so the design required a soil-cement-bentonite cutoff wall that was not in the bid.

What it cost. 26 weeks of extra programme and $5.8M of additional cost. As a design-bid-build contract with a differing-site-conditions clause and pre-bid geotechnical data relied upon in our bid, we recovered $4.9M of that through the modification process. We carried the balance.

What changed. We now commission our own geotechnical investigation, our own boreholes, our own geologist, our own risk register, on every levee, dam and channel project we price, regardless of what the owner provides. It costs roughly 0.3% of contract value and we will not bid flood control work without it.

References

Ask them, not us.

Every owner below has agreed to be contacted directly about our performance. We will provide names, telephone numbers and email addresses on request.

Heavy Civil

Colorado Department of Transportation

I-70 Floyd Hill Segment 3 · $214M · progressive design-build · 2022–2026

Energy

Cascade Power Authority

Cascade Ridge pumped storage and Denali 230 kV rebuild · $446M combined · 2021–2025

Government

U.S. Army Corps of Engineers

Tulsa and Albuquerque Districts · hangar modernisation and levee restoration · $110M combined

Mining

Thunder Basin Resources LLC

Bighorn Basin pre-strip and contract mining · $172M term contract · 2019–present

Industrial

Ohio River Terminals Group

Bluegrass rail and bulk terminal · $121M · design-build · 2021–2024

International

Andean Copper Joint Venture

Antofagasta concentrator expansion · $245M · design-build · 2020–2024